The Cheniere Energy SPLNG Facility will consist of four (4) LNG compression trains. Approximately 32,000 Square precast, prestressed concrete piles have been selected as deep foundation support for Trains 1 through 4 as well as the marine Roll on Roll off (RORO) Bridge and marine dock structures.

Services Provided: High-Strain Dynamic Testing, Static Pile Load Testing and Construction Materials Testing. Technicians performed up to 3 dynamic tests per shift using PBI PAX equipment.

Contractor: Bo-Mac Contractors, Ltd.

Owner: Cheniere Energy

Completion Dated: Active (Estimated Summer 2014)